© 2024, all rights reserved. Site by Online Designs
- September 22, 2021
Kaanga Ma wins community vote
Ngā mihi mō au korero whakahoki!
Thank you for your feedback. We had a fantastic response to our recent survey asking for help to select one of the trial crops for Kaipara Water demo site two. The winner by community vote was kaanga ma.
Kaanga ma is a traditional Māori corn used to make fermented corn and other recipes. It can also be used as a flour corn. It has large pearl-coloured kernels, and is similar to the most popular old type of corn in South America and the most popular posole corn in the USA.
It will be planted alongside soybean/edamame, beetroot, and watermelon on Kaipara Water demo site two, in Te Kōpuru. The crops will be watered using a 242-metre span centre pivot irrigator which can irrigate up to around 10 hectares. Water will be gradually taken from a nearby creek under an existing resource consent.
The other demo site is on iwi land at Maunganui Bluff north of Dargaville. The project team are working with Te Roroa to showcase irrigation that can be easily scaled up or down, depending on what crops are being watered. The site includes an in-ground irrigation system managed remotely via a web application to deliver water and fertiliser to vegetable crops in precise amounts. Four trial crops will also be planted on this site – yam, kamokamo, watermelon, and sweetcorn.
Building on Kaipara Kai, the Kaipara Water demonstration sites showcase smart water use through different irrigation techniques and the ways in which this can support high-value crops. Northland Inc. are contracted to manage the two sites.
Check out the planting plans for each site below, as well as crop selection info.
Demo site one trial crops
- Yam NZ yams are harvested later as tubers do not form until late in season, and requires earthing up like potatoes. Yield and quality are heavily affected by irrigation, and their commercial success is likely to result from their acceptability to the consumer in terms of colour, size, and taste. Could be part of crop rotation with cereal crops.
- Watermelon Already commercially grown in Kaipara District but there are new varieties to trial. There will be trialling with irrigation amount as well as planting later than normal to extend season.
- Kamokamo A traditional crop, kamokamo has been grown commercially in Kaipara District in the past. Although tolerant to drought crop yield is better with irrigation. Can only be watered from below.
- Sweetcorn Kaipara has the potential to develop a niche position as a trusted supplier of early season fresh sweetcorn targeting the Auckland market. Many parts of Kaipara have the right soil and climatic conditions for production of sweetcorn.
Demo site two trial crops
- Beetroot Kaipara already has proven capabilities in root crops with kumara. Can be grown year round, and as part of rotation with other crops. Needs regular irrigation to prevent to avoid going woody, will be looking to improve root yields with irrigation trial.
- Soybean/edamame Soybeans fix nitrogen in the soil and provide a large yield of a versatile crop with numerous uses. Kaipara District has the climatic conditions and water required to produce soybeans in commercial quantities, but it is not commercially grown here currently. Can be grown on most soil types but yields vary.
- Watermelon Already commercially grown in Kaipara District but there are new varieties to trial. There will be trialling with irrigation amount as well as planting later than normal to extend season.
- Kaanga ma A traditional Māori corn used to make fermented corn and other recipes. It can also be used as a flour corn. It has large pearl-coloured kernels, and is similar to the most popular old type of corn in South America and the most popular posole corn in the USA.
Keep an eye out for details of the community open day for each site coming in November.
Kaipara Water is part of the Kaipara KickStart projects, alongside Roads, Wharves and Kai, led by Kaipara District Council. Water plays a key part of transforming land use. Building on Kaipara Kai, the Kaipara Water project will further support valuable Kai opportunities. We have set up two demonstration sites within the community, working with the landowners to showcase smart water use and the ways in which this can support specific crops. Kaipara Water is supported by PGF funding from Kānoa – Regional Economic Development & Investment Unit.
Level 2 water restrictions in place for Baylys Beach and Dargaville
- December 09, 2024
Residents in Baylys Beach and Dargaville on town water supply are asked to conserve water use as we enter level 2 water restrictions.
Read moreMilestone upgrade for flood protection system
- November 29, 2024
A major upgrade to the Raupō drainage system to protect highly productive fertile land has made significant progress.
Read more- November 06, 2024
A new observation tower for Baylys Beach will improve the response times and working conditions for volunteer lifeguards on the popular west coast beach.
Read more- September 26, 2024
The relationship agreements Kaipara District Council holds with Te Roroa and Te Uri o Hau were terminated by the Council at its September meeting, with a view to start afresh with new agreements.
Read more- September 12, 2024
A new strategy developed by Northland’s four local authorities looks to improve accessibility across the region, which has the country’s second highest rate of disabilities and impairments.
Read more- September 09, 2024
It’s Welcoming Week, an opportunity to make our communities more welcoming to all those who choose to call Aotearoa New Zealand home.
Read moreBoost to accelerate recovery efforts
- August 30, 2024
A suite of recovery and resilience projects underway in Kaipara District is set to benefit from more than half a million dollars in central government funds.
Read moreCouncils join forces to tick off last road recovery repairs
- July 03, 2024
Kaipara District Council and Whangarei District Council are developing a joint panel of contractors to complete the remaining emergency recovery repairs, helping to save money and time for both councils.
Read more- June 21, 2024
Downer is working hard to get construction done through the winter period, in time to have the third phase of the shared path open for use when summer rolls round again.
Read moreLarge crowd turns out to celebrate new Pouto wharf
- June 14, 2024
Close to 100 people came together at the southern tip of the Pouto Peninsula to celebrate the opening of a new wharf in Kaipara.
Read moreWaters infrastructure projects better off thanks to redirected funding
- May 31, 2024
More than $3.2million of external funding will be redirected into Kaipara District’s waters infrastructure budget after Council deciding to redirect existing uncommitted Better Off and Transition Support funding.
Read moreLevel 3 water restrictions lifted for Dargaville and Baylys Beach
- April 23, 2024
Water restrictions have been lifted for properties on town supply in Dargaville and Baylys Beach.
Read more- March 20, 2024
Dargaville and Baylys Beach residents have responded to the call to preserve water under Level 3 water restrictions.
Read more- March 07, 2024
Work on Pouto wharf has been progressing well during weather and tidal windows, with the crew taking every opportunity to complete piling works, concreting, and install bearers. With most of the piles now in place, the crew are focused on completing the bracing and joists over the next fortnight.
Read more- February 23, 2024
Residents in Dargaville and Baylys Beach are urged to reduce water use after use has risen slightly since Level 3 water restrictions came into force on 12 February.
Read more- February 12, 2024
Water restrictions have been introduced for Dargaville and surrounds, with residents across the entire Kaipara district being urged to use the precious resource wisely.
Read more- January 29, 2024
Our district is buzzing with summer. Everywhere I go in Kaipara our communities and our many visitors can be seen making the most of these sunshine hours.
Read moreWeather causes further delays to Pouto wharf completion
- November 20, 2023
Another round of weather events, including ex-Cyclone Lola, has affected works on Poutō wharf and extended the completion date out to the end of the summer.
Read moreSuite of renewals and upgrades shores up water resilience
- October 24, 2023
A number of infrastructure renewals and upgrades completed in recent years have strengthened water security in Kaipara.
Read moreCalling on the community to support reading for pleasure and wellbeing
- September 25, 2023
Soon, Dargaville and Te Kopuru locals will see little libraries popping up around the community.
Read more- September 19, 2023
Summer is on its way and it’s time to start preparing for a drought. Meteorologists are predicting a dry windy summer.
Read moreRemoving problem trees to build Northland's resilience and warm its people
- September 05, 2023
A new collaborative project has arisen from the aftermath of Cyclone Gabrielle, which aims to build Northland’s resilience to future adverse weather events by tackling the problem of fallen and at-risk trees.
Read moreTe Ara o Te Whai - Mangawhai boardwalk opens to public
- August 31, 2023
Sunny weather and an incoming tide provided the perfect backdrop to open the Mangawhai boardwalk to a large gathering last week.
The boardwalk is the second phase of the Mangawhai shared path project, connecting the village to the heads, and making it safer and easier to travel by foot, bike, or scooter along busy Molesworth Drive.
Read moreNorthern Wairoa River flood prevention
- August 08, 2023
An update from Kaipara District Council and Northland Regional Council.
Read moreSecond phase of Mangawhai shared path nears completion
- July 10, 2023
Progress has been tracking well on the second phase of the Mangawhai shared path, with the boardwalk section now stretching right across the water by the causeway.
Read more- July 05, 2023
Work to improve the resilience of Maungaturoto’s water network is almost complete.
Read morePoutō wharf construction work temporarily suspended until September
- June 27, 2023
Contractors working on the finishing touches for Poutō wharf have had to down tools until conditions are more favourable to complete the remaining piling and wharf head.
Read more- June 15, 2023
Kaipara District Council Parks and Open Spaces team manage six of the district’s cemeteries and recently funded community-led work to repair the gates to their former glory.
Read more- June 13, 2023
A sunny day set the scene for the official opening of Stage One of the Kaihu Valley Trail (KVT), which was celebrated with a blessing and ribbon cutting ceremony hosted by Ahikiwi Marae on Saturday 10 June.
Read more
Permanent upgrade of Wood Street to start next year
- May 08, 2023
Construction of the permanent upgrade for Wood Street will take place next year, after Council has signalled prioritising emergency works over planned projects for the upcoming Annual Plan 2023/2024.
Read moreFarmers and growers attend Kaipara Water Demonstration Site field visit
- April 12, 2023
Late last month a warm Kaipara sun shone on a group of farmers and growers keen to hear about a season of growing squash in Maunganui Bluff, north of Dargaville.
Read moreMessage from Mayor Craig Jepson - Dargaville flooding
- February 14, 2023
In the early hours of this morning Awakino River on the northern outskirts of Dargaville breached its banks.
Read moreCar wreckage removed from Pouto Point
- January 25, 2023
Salt services, a professional dive team, spent most of a day early last week pulling an old car wreck out of the water. The car had been submerged some years ago and was resting where work was starting on the wharf head.
Read morePot unlocked for Pouto Point amenity improvements
- January 10, 2023
Improvements to the Poutō Point carpark area can progress in 2023 thanks to further funding from Kaipara District Council.
Read more- December 22, 2022
The growing season for the Kaipara Water demonstration sites has kicked off with the Maunganui Bluff site planted out with squash earlier this week.
Read more- December 15, 2022
Northland motorists are being asked to be patient this summer as the Northland Transportation Alliance battles relentless wet weather while attempting roading repairs.
Read more- December 15, 2022
Summer is here and so are all our visitors. It’s the busiest time of the year for the Taharoa Domain, and we need you to help us look after this beautiful gem.
Read more- December 13, 2022
The four councils in our region are working together on a plan to make our communities more accessible to live, work, play and visit.
Read morePouto wharf takes shape
- December 09, 2022
The construction of Poutō wharf has really been trucking along recently, with another dozen piles driven in the ground last week.
Read moreWaka Kotahi funds to support walking and cycling in Dargaville
- December 05, 2022
Waka Kotahi NZ Transport Agency is encouraging people in Dargaville to get on their bikes with a Transport Choice programme grant of approximately $8,000,000 to be provided to Kaipara District Council, announced on 4 December 2022.
Read more- November 07, 2022
If you live in Poutō or have gone for a drive down recently, you will have seen some of the wharf construction taking shape.
Read more- September 29, 2022
Physical works for Poutō wharf have begun. Earlier in the month, Waikaretu marae led a blessing ahead of construction starting.
Read more- September 21, 2022
A chainsaw course for Dargaville High School students saw wattle and other pest plants removed from Old Mt Wesley cemetery.
Read moreCouncil collaborates with Te Uri o Hau on boardwalk design
- September 16, 2022
The second phase of the Mangawhai shared path cranks up construction next month, and includes a collaboratively designed boardwalk running alongside the causeway.
Read moreSunflowers and squash to brighten Kaipara Water demonstration sites
- September 15, 2022
Kaipara District Council has confirmed sunflowers and squash for the second growing season of the Kaipara Water demonstration sites.
Read moreKaihu Valley Trail September update
- September 08, 2022
An update on the Kaihu Valley Trail including fencing progress, funding and latest finds along the trail.
Read morePouto wharf works get set to kick off
- August 24, 2022
Work to construct Poutō wharf is set to begin shortly.
Read moreCouncil improves system resilience
- August 23, 2022
The first part of a multi-phase project to manage Council’s water and wastewater asset network more efficiently and improve its resilience is complete.
Read moreThree waters explained
- July 20, 2022
Government sources estimate that between $120 and $185 billion dollars of investment in three waters (drinking water, waste water and storm water) infrastructure will be needed over the next 30 years to improve the quality of our drinking water and wastewater and stormwater management, across New Zealand.
Read more- June 27, 2022
Kaipara District Council’s operations and maintenance switches over to a new contractor next month.
Read morePlanting pohutukawa, nikau along the shared path
- June 08, 2022
With the courtesy crossings for phase one now complete, the Mangawhai shared path team and contractors got the spades and mulch out and ticked off the planting, getting the final shrubs and trees in the ground last week.
Read more- May 24, 2022
Down the road from the mighty Tāne Mahuta, a road-carpet was rolled out and lights set to green as the newly sealed 1.5km stretch of Waipoua River Road was opened for traffic.
Read moreTe Tai Tokerau councils adopt region-wide climate adaptation strategy
- May 11, 2022
Te Tai Tokerau councils celebrated a unique milestone in April after the adoption of New Zealand’s first region-wide climate adaptation strategy.
Read more- April 26, 2022
Complex problems for councils seldom come as neatly packaged as the “Better Off” funding which is part of the Three Waters Reforms.
Read moreAdditional funding for Pouto wharf confirmed
- April 14, 2022
Elected Members have unanimously approved paying the forecasted $265,000 project shortfall for Poutō wharf, funded from the district’s financial contributions reserves.
Read moreKaihu Valley Trail April update
- April 13, 2022
Check out the latest happenings on the Kaihu Valley Trail progress, including the discovery of some railway artefacts.
Read more- March 30, 2022
Two new footbridges were opened at a double ribbon-cutting ceremony in the Kaipara township of Kaiwaka on Saturday 26 March.
Read more- March 18, 2022
We are aware some Maungaturoto residents have recently experienced events of low pressure or in some instances disrupted water supply to their properties.
Read moreHarvest begins across demonstration sites
- March 16, 2022
Harvesting is underway across the Kaipara Water demonstration sites.
Read more- March 11, 2022
Ongoing COVID-19 restrictions and other delays to the programme have inevitably slowed the Poutō wharf project, but the team have made progress and are now working through the tail end of the developed design.
Read more- March 07, 2022
At a recent Council meeting, staff gave an update on Gumdiggers Track and the work happening behind the scenes.
Read moreIndicative general rates rise in line with Long Term Plan
- March 04, 2022
At a recent briefing Council staff presented the preliminary financial statements for the upcoming Annual Plan (2022-2023).
Read moreWater storage plan to ease Dargaville water restrictions
- March 02, 2022
The Waiatua Dam (on Opanake Road) may be the solution to end the Dargaville and Baylys Beach water shortages, according to a preliminary investigation, commissioned by Kaipara District Council.
Read more- February 24, 2022
Locals and visitors with their boogie boards, beach bags, skateboards and shopping bags piled on board the Mangawhai Village to Beach bus over summer, turning out in even greater numbers than previous years of the trial service.
Read more- February 24, 2022
At yesterday's Council meeting, the Kaipara District Council approved paying the forecasted $487,000 sealing project shortfall to complete Pouto Road Phase 1, from its retained earnings.
Read moreMolesworth Drive shared path works
- February 16, 2022
Starting today through to Wednesday 23 February a short section of Molesworth Drive from the ITM down to Nautical Heights will go down to one lane, with flow managed using traffic lights.
Read more- February 16, 2022
Last week saw the installation of a temporary sign marking the Dargaville entrance of the Kaihu Valley Trail.
Read more- February 11, 2022
The council is upgrading wastewater systems and is asking people to flush responsibly.
Read moreSmart water use supports growth across diverse crops
- February 08, 2022
Growth is the word of the day when it comes to the Kaipara Water demonstration sites. The summer months have seen the former grassed paddocks turn into a jungle of green activity on both sites.
Read more- February 04, 2022
The Ministry for Business Innovation and Employment (MBIE) has released the $3.5M needed to protect existing stopbanks against flooding, along the western side of Wairoa River between Dargaville and Te Kopuru.
Read more- February 04, 2022
The Northland Transportation Alliance’s (NTA) Unsealed Road Improvement Project remains on track to approved project milestones with 84.4 km’s of the network’s road pavement layering completed to date.
Read moreTwo thirds of Maungaturoto raw watermain renewal work completed
- February 02, 2022
Work is progressing well on the raw watermain renewals in Maungaturoto.
Read morePouto Road phase one and Waipoua River Road nearing completion
- January 28, 2022
Pouto Road phase one and Waipoua River Road will be completed in April, despite delays caused by wet weather in the Kaipara District post the Christmas break.
Read more
- January 28, 2022
Upgrades to numerous unsealed Northland roads are well underway, with a substantial amount of work to be completed by the end of June in the Kaipara District.
Read more- January 28, 2022
Although recent rain has been welcomed by landowners, it is causing headaches for Kaipara District Council’s Raupo stopbank improvement project, in Ruawai.
Read moreDawn blessing opens the Pahi wharf upgrade
- December 21, 2021
Construction for the Pahi wharf upgrade ended as it began months ago, with the sky lighting up slowly on the people gathered together. Voices joined in karakia and waiata, led by kaumatua Hone Martin and representatives of Te Uri o Hau swirled around the Kaipara harbour as a dawn blessing was performed to open the wharf’s gangway and pontoon.
Read moreVillage intersections and shared path - December 2021
- December 15, 2021
With the border opening there will be increased traffic travelling through both of the worksites. Please remind your visitors ahead of their arrival that these are still active work sites in the lead up to the break – give your friends and family a heads up so they can be prepared for possible travel delays and can plan their journeys accordingly.
Read more- December 09, 2021
Kaipara District Council’s externally funded Unsealed Road Improvements Project remains on track with a little over half the project completed. Northland Transport Alliance Maintenance Lead Bernard Petersen says this includes just over 70 kilometres of unsealed surfaces upgraded.
Read moreSeeds sown for Kaipara Water demonstration sites
- December 03, 2021
Visitors to the Kaipara Water demonstration sites will spot the beginnings of green growth starting to peek through the soil.
Read more- December 01, 2021
As part of ongoing improvement of Kaipara’s unsealed roading network, the Northland Transportation Alliance is using Ground Penetrating Radar (GPR) to confirm pavement thickness safely and rapidly across the district.
Read more- December 01, 2021
It begins! Fulton Hogan started physical works to improve Waipoua River Road this week.
Read more- November 25, 2021
Our Kaipara District Council team is excited to see the sealing start to roll out for Phase one of the Pouto Road project – the upgrade of the northern portion running down to Ari Ari Road junction.
Read moreOver $4M spent on Unsealed Roading Network in 2021
- November 18, 2021
The $8.06M Unsealed Roading Network project that began in May last year, has crossed the halfway mark with completion of the first season’s physical pavement and associated works at a cost of $4.3M to end of October.
Read more- November 15, 2021
A blessing undertaken by Te Roroa last week marked the start of physical works on Waipoua River Road.
Read more- November 15, 2021
Extra low tides earlier this month allowed Huband Contractors to work on some of the timber repairs around the lower parts of the tidal stairs.
Read morePouto wharf construction to start in 2022
- November 03, 2021
Construction work for the new Poutō wharf will begin in 2022.
Read moreWaipoua River Road works set to start
- November 02, 2021
An onsite blessing will be held by Te Roroa on Friday 12 November to mark the start of construction on the $1.8m Waipoua River Road project.
Read moreWork starting on Maungaturoto's raw watermain pipes
- October 22, 2021
Over the next few months, our team and contractors will replace approximately 3,000m of ageing raw watermain pipes.
Read moreSecond LittaTrap audit reveals increase in rubbish
- October 15, 2021
Findings of the latest LittaTrap audit found an increase of rubbish captured. LittaTraps (a simple, cost-effective net that sits inside a stormwater grate) have been installed around Northland through a multi-agency initiative.
Read moreWork on the Pahi wharf upgrade continues at pace
- October 12, 2021
The Huband crew have been working at the end of the wharf recently, preparing the connection for the new gangway, and replacing pile caps and stringers.
Read more- October 06, 2021
If you’re connected to Council’s treated water supply system, your most recent water invoice may have shown an increase in the cost for your first cubic meter of water.
Read moreLetter from KDC to Hon Nanaia Mahuta
- September 30, 2021
Considerations from Kaipara District about the Three Waters Reforms.
Read morePahi wharf upgrade - old handrails come down, new ones go up
- September 22, 2021
It’s been a hive of activity down at the Pahi wharf recently. The upgrade has started with local contractors Huband carrying out the carpentry and repair work on the wharf.
Read more- September 09, 2021
Dawn broke over the land and water this morning, as Te Uri o Hau kaumātua Hone Martin led a blessing ceremony to begin construction down at Pahi wharf.
Read more
- September 09, 2021
Spring has sprung and so has action at our Kaipara Water sites. The project team is busy with planting plans and site preparation and now we need your help.
Read moreNew Reserve Management Plans for Pou Tu o Te Rangi and Harding Park
- August 25, 2021
Council and the Pou Tu o Te Rangi Joint Management Committee are preparing new reserve management plans (RMPs) for the Pou Tu o Te Rangi historic reserve and Harding Park (including the adjoining Old Mount Wesley Cemetery).
Read more- August 11, 2021
Kaiwaka township has seen a number of safety improvements recently, with our team and contractors Ventia busy working along Kaiwaka-Mangawhai Road.
Read moreGreen light to accelerate intersection improvement works in Mangawhai Village
- August 10, 2021
A significant change in the programme for the much-needed Village intersection improvements will see the work finished in early December, ahead of schedule.
Read moreWorks progress on Mangawhai intersection improvements and shared path
- July 28, 2021
The United Civil team are starting to work in the road (Stage Two of their work staging plan), focusing on the area at the western entrance to the Moir Street / Insley Street intersection.
Read moreUnsealed road improvement works progressing
- July 28, 2021
Winter weather has slowed the reconstruction work to upgrade our unsealed roads, but no time is being wasted. Teams are clearing vegetation and drains in preparation for when reconstruction work can start again.
Read more- July 12, 2021
Kaipara District Council has been awarded a grant from the Creative NZ Local Government Arts Fund to develop an Arts, Culture and Heritage Strategy.
Read more- July 09, 2021
Kaipara District Council voted to become a shareholder of Northland Inc. at their meeting on 26 May.
Read more- July 01, 2021
The Kaihu Valley Trail is a 40km walking and biking track being constructed from Dargaville to Donnellys Crossing. It will form part of the Ancient Kauri Trail that extends from Omapere to Maungaturoto and be one of the 23 Great Rides around New Zealand.
Read moreCouncil responds to community submissions in Long Term Plan decisions
- June 30, 2021
Kaipara District Council today endorsed a future-focused Long Term Plan (LTP) which aims to respond to a growing population while caring for the environment and keeping rates increases low.
Read moreWork starts on Mangawhai Village intersection improvements
- June 01, 2021
Construction work on the Mangawhai Village intersection improvements started this week.
Read moreInfrastructure renewal projects roll out across the District
- May 19, 2021
Nine infrastructure renewal projects are being rolled out across Kaipara District this year.
Read more- May 19, 2021
The Kaipara Kai Hub team have been in the news a lot recently with all their peanut trial mahi!
Read more- May 10, 2021
Kaipara District Council has developed a new formula for unsealed roads that results in a more durable, and lower maintenance, surface.
Read moreLake Taharoa clean up discovers lost treasures and rubbish
- April 15, 2021
A friendly reminder to take only photos and leave only footprints at the Taharoa Domain when exploring the wonderful jewel of Kaipara.
Read more- April 13, 2021
In the first few months of 2021 there’s been a trickle of new information which has led to a substantial update on the long-running story of the debt levels of Kaipara District Council’s Mangawhai Wastewater Scheme.
Read more- April 07, 2021
Kaipara District Council has published a report about the outstanding historic debt and capacity of the Mangawhai Wastewater Scheme (MWWS).
Read more- April 06, 2021
Our Parks team and local contractors Turf Tamer recently completed work by the Kaiwaka River (north eastern side of the bridge).
Read moreHistoric Daring schooner approved to berth temporarily next to Mangawhai Museum
- April 01, 2021
Kaipara District Elected Members have voted in favour of a proposal to temporarily store the 157-year-old ship the Daring next to the Mangawhai Museum.
Read more- April 01, 2021
Work will begin again at the Mangawhai Community Park after the Easter break.
Read more- March 24, 2021
Recently we received the good news that Waka Kotahi NZTA have granted funding to complete phase 1 of our new shared path.
Read more- March 22, 2021
The first part of the Pouto Road sealing project is set to start this week from Wednesday 24 March, kicking off one of Kaipara’s most significant road sealing projects.
Read more- March 09, 2021
We recently started the evaluation for the Wood Street revitalisation project.
Read more- March 05, 2021
Two footbridges are to be erected in Kaiwaka, parallel to State Highway 1 and crossing streams at the northern end of the township.
Read moreRecord numbers jump on board for Mangawhai's Village to Beach Loop Bus Service
- February 22, 2021
Mangawhai’s bus service proved hugely popular with both locals and visitors this summer. The bus ran daily 27 December – 17 January and then every weekend and public holiday to 08 February, picking up passengers from Mangawhai Village to the surf beach.
Read morePlan to grow a better Kaipara shaping up
- February 10, 2021
Kaipara District Council has laid out its vision for the next decade of development in its Long Term Plan (LTP) and is asking the community if they agree.
Read moreMotu Wheteke blessing marks reopening of quarry for Pouto Road sealing project
- February 09, 2021
Earlier this month Rīpia Marae representatives blessed the site of Motu Wheteke, ahead of physical works starting at the quarry. Kaipara District Council contractors are preparing to reopen the site, primarily for the Provincial Development Unit-supported Pouto Road sealing project.
Read more- January 29, 2021
The Kaihu Valley Trail is one section of the Ancient Kauri Trail that will be developed in stages and eventually link Ōmāpere, on the Hokianga Harbour, to the Mangawhai Coast.
Read more- January 27, 2021
Since our last update, the Kaipara Kai Hub team has been busy managing crop trials, engaging with local growers looking at crop diversification, and supporting the kick-off of local projects. The trial site at Te Roroa’s Kai Iwi farm is looking lush.
Read moreWood Street Revitalisation Project Recent Survey Results
- January 26, 2021
Thanks very much to everyone who took the time to fill out our recent Wood Street survey. We had a good response with a total of 205 people selecting one of four options to reconfigure the parking near the entrance to Wood Street (from Molesworth Drive).
Read more- January 25, 2021
If you're out and about around Lorne, Pirika, and Haimona Street, you may spot our team and contractors undertaking work on the Dargaville water mains.
Read moreWood Street revitalisation project: Feedback wanted for entrance survey
- January 20, 2021
The interim design for the Wood Street revitalisation project has been in place since early December 2020.
Read more- January 19, 2021
‘Water’ will be a word to watch in 2021, as far as Kaipara District Council is concerned. To start with,
low river flows mean water restrictions are in place for our largest reticulated town supply to Dargaville
and Baylys Beach.
- January 13, 2021
Changes at Wood Street are part of the Wood Street revitalisation project, a community co-design that came about after the Mangawhai Business Association approached Council in 2019.
Read more- December 17, 2020
The FREE Village to Beach Loop bus service is running again this summer. Please let your family, friends, and all your visitors know. The bus service is free for everyone.
Read more- December 16, 2020
The first concrete pour was completed for the new pathway at Matakohe earlier this month.
Read more- December 16, 2020
Kaiwaka footbridges will form part of the Kaiwaka walking and cycling network and will reduce severance caused by the state highway and rivers.
Read moreCommunity collaboration leads Wood Street revitalisation project
- December 14, 2020
After months of planning, the Wood Street revitalisation project really got rolling this month, with key changes implemented following the latest community co-design workshops.
Read more- December 08, 2020
We are go! Traffic is now one way on Wood Street. Entry is via Molesworth Drive (similar to last summer’s trial). Please take care and look out for the new road markings and signs.
Read more- December 02, 2020
From tomorrow (Thursday 03 December) Wood Street will change to a one way traffic system. Entry will be via Molesworth Drive (similar to last summer’s trial). Please take care and look out for the new road markings and signage, which will be in place from this Thursday. Wheel stops are also being installed to complete the improvements to the back carpark.
Read more
Long Term Plan 2021/2031 update
- December 02, 2020
See the results from surveys and events we've undertaken recently as part of our Long Term Plan.
Read more- November 30, 2020
Our contractors and their team are starting work on some of the improvements to the Mangawhai Community Park facilities later this week.
Read more- November 24, 2020
The weather turned out and so did the people. The Marine Hall was buzzing recently during a community open day for the proposed Pouto wharf.
Read more- November 23, 2020
Have you ever looked at a verge or berm around your area and wondered why it has a dip in its centre? That subtle depression is doing an incredibly important job – it’s called a swale and they're an essential part of our stormwater services.
Read moreKickStart Water demonstration sites approved by Kaipara District Council
- November 18, 2020
Two proposed demonstration sites for the Kaipara Water project have been given the green light from Council, which will serve as real-life working examples of the best ways to irrigate high value horticultural crops.
Read more- November 17, 2020
How can we make Northland more accessible for people with disabilities, older adults, migrants, or families with young children?
Read more
Works start for Wood Street revitalisation project
- November 16, 2020
Works on the Wood Street interim design will be starting later this week!
Read more- November 16, 2020
Ruawai Water treatment plant played host to a number of local school kids as part of the EnviroSchools Water for Life
programme last week. The programme is a Northland Regional Council initiative.
- November 11, 2020
Hats off to the Ngā Uri o Hau Native Nursery team! They have been busy replanting some of the areas down at Mangawhai Community Park recently.
Read more- November 05, 2020
Construction has started on the new Baylys Beach walkway. The work is led by Kaipara District Council, with a $300,000 grant received through the Tourism Infrastructure Fund.
Read more- November 04, 2020
Find out more about the new Pouto wharf at our upcoming community open day.
Read more- November 04, 2020
The beautiful stretch of weather we’ve been enjoying is great for the beach, but not for water supplies. Being wise with water at the beginning of the season can ease the pressures later on. Let’s streeeeeeech the supply as far as we can.
Read more- November 04, 2020
There’s been a lot of exciting mahi happening in Taharoa Domain recently. This year our Parks team and their contractors have planted more than 12,500 native trees as part of a regenerative planting plan and a successful pest cull has been undertaken around the Kai Iwi lakes area.
Read more- November 04, 2020
Kaipara District Council has used funding under the Te Tai Tokerau Redeployment Package to complete some exciting roadside projects. The funding package, through the Provincial Growth Fund, is providing urgent economic relief for those affected by the COVID-19 pandemic, by creating immediate work opportunities for local people.
Read moreFire Station makes way for new shared space in Wood Street
- November 03, 2020
Fire Station cleared in Wood Street.
Read more- October 29, 2020
Kaipara District Council is seeking feedback on proposals to set new speed limits in the Mangawhai and Kaiwaka areas, including the Mangawhai urban area.
Read moreKaipara District Council awards funding to 19 community organisations
- October 28, 2020
More than $180,000.00 has been awarded in the latest Kaipara District Council funding rounds for Reserve Contributions Contestable Fund, Rural Travel Fund, and the Creative Communities Scheme.
Read more- October 09, 2020
Collaborative stormwater project kicks off with first LittaTrap installed in Mangawhai
Read moreWork progresses in Kaipara under Te Tai Tokerau Redeployment Package
- September 09, 2020
Work is progressing at pace, as a result of $2.87m recently allocated to Kaipara District from the Te Tai Tokerau Redeployment Package. A total of $9.32 million is allocated across Northland. The funding package through the Provincial Growth Fund is providing urgent economic relief for those affected by the COVID-19 pandemic, by creating immediate work opportunities for local people and businesses.
Read moreKaipara District Council announces second stage of Pouto Road upgrade
- September 09, 2020
Approval from the Provincial Growth Fund and the release of $2.8 million means Kaipara District Council can progress with sealing the second section of Pouto Road (Phase 2).
Read more- September 04, 2020
Kaipara District Council Elected Members opted in to the first part of a reform of the three waters system when they signed a Memorandum of Understanding (MOU) at the end of August.
Read moreKaipara District Council awards funds to 12 Mangawhai organisations
- September 01, 2020
A total of $132,320.00 has been awarded in the latest funding round for the Mangawhai Endowment Lands Account (MELA).
Read more- August 28, 2020
Minister Shane Jones has announced $15 million for Kaipara District Council for shovel ready infrastructure projects
Read moreKaipara District Council approves old Mangawhai Fire Station to be demolished
- August 26, 2020
Councillors this morning voted in favour of the former fire station building at 09 Wood Street to be demolished.
The Council owned building is unoccupied. The Mangawhai Fire Station has been in its new modern premises at 191 Molesworth Drive since late 2019.
Read more- August 13, 2020
Construction work for the new Dargaville pontoon is set to begin next month. The work is part of Kaipara KickStart, an umbrella programme led by Kaipara District Council and funded by the Provincial Growth Fund, to grow the district’s economy and increase community wellbeing.
Read moreKaipara District Council awards funds to 41 community groups and organisations
- July 17, 2020
More than $122,000 has been awarded in the latest Kaipara District Council funding rounds for Community Grants, Rural Travel Fund, and Creative Communities Scheme.
Read moreFree online talk on current and future crop suitability in the Kaipara District
- June 25, 2020
An online talk with NIWA, Plant & Food Research, and Manaaki Whenua – Landcare Research will present valuable climate and soil research for the district’s landowners.
Read moreKaipara District Council announces Wood Street revitalisation funds
- June 25, 2020
Waka Kotahi NZ Transport Agency has awarded funds to Kaipara District Council for the next stage in the Wood Street revitalisation project. The funds are part of the Innovating Streets programme and pilot fund, which supports councils to deliver more vibrant and people-friendly public spaces by employing ‘tactical urbanism’. The grant will fund 90 percent of an interim treatment that will inform a permanent future upgrade in Wood Street.
Read moreKaipara District Council Announces Final Wharves Feasibility Study and Programme Business Case Approval
- May 29, 2020
Approval from MBIE on the Kaipara Water Transport Network and Wharves Feasibility Study and Programme Business Case means the Council can embark on the next stage of the project.
Read more- May 18, 2020
An online talk hosted by the Kaipara District Council will present valuable opportunities for the district’s landowners, and other businesses related to the horticulture industry.
Read more- March 04, 2020
Kaipara Kai, a support base for landowners and the kai industry was opened for business in Ruawai by Hon. Shane Jones today.
Read more