Roading report - December to January 2025
- February 24, 2025
Work across the 1126km unsealed network will pick back up in late March, having slowed down during the dry season.
Read more
Roading report - October 2024
- November 14, 2024
In October, Kaipara's roading team powered through 55% of necessary pre-seal works, in preparation for re-seals next year.
Read more
June roading report
- July 18, 2024
We made the most of June’s relatively dry weather, carrying out culvert placements and water tabling across the district.
Read more
April roading report
- May 08, 2024
Roading teams made the most of April’s dry weather, resurfacing 129,042m2 across the network and carrying out culvert replacements and water tabling.
Read more
December roading report
- February 12, 2024
Our roading teams worked hard throughout December to prepare our roads for a surge in traffic over the summer.
Read more
October roading report
- December 12, 2023
Despite the unexpected interruption from Cyclone Lola,October was a very productive month on roads across Kaipara.
Read more
September roading report
- October 17, 2023
We are only just on the other side of Winter and are already feeling the benefits of warmer and drier weather.
Read more.png)
August roading report
- September 29, 2023
The end of another winter gave us some much-needed sunshine and blue skies. Now with Spring upon us and the days getting longer, our focus moves to pavement works.
Read more
Kaipara's July roading report
- August 24, 2023
The rainy weather persisted through July, resulting in 949 new pothole reports. To tackle the pothole issue, we introduced an additional pothole truck to speed up repairs.
Read more
Kaipara's June roading report
- July 19, 2023
The unsealed network has remained a significant point of focus throughout this traditionally rainy month.
Read more
Kaipara's May roading report
- June 19, 2023
It’s been nearly six months since Cyclone Gabrielle, however we are still actively repairing damages and working through a substantial backlog.
Read more
Kaipara's April roading report
- May 11, 2023
This month, we have been primarily focused on clearing slips, performing tree and drainage works, and continuing with the unsealed rehabs program.
Read more