Kaipara's July roading report
- August 24, 2023
The rainy weather persisted through July, resulting in 949 new pothole reports. To tackle the pothole issue, we introduced an additional pothole truck to speed up repairs.
Read more
Kaipara's June roading report
- July 19, 2023
The unsealed network has remained a significant point of focus throughout this traditionally rainy month.
Read more
Kaipara's May roading report
- June 19, 2023
It’s been nearly six months since Cyclone Gabrielle, however we are still actively repairing damages and working through a substantial backlog.
Read more
Kaipara's April roading report
- May 11, 2023
This month, we have been primarily focused on clearing slips, performing tree and drainage works, and continuing with the unsealed rehabs program.
Read more
Kaipara's March roading report
- April 11, 2023
Our roading team were kept busy all summer, responding to urgent roading issues following the extreme weather events we’ve had.
Read more
Ruawai: Calling on Local Knowledge
- March 15, 2023
The Ruawai Adaptive Pathways Community Panel is inviting the Ruawai community to help shape their planning by sharing local knowledge through an online survey or at a community drop-in session.
Read more
Response to Cyclone Gabrielle continues
- February 23, 2023
Kaipara District continues to respond to the impacts of Cyclone Gabrielle.
Read more
Road conditions Friday 3 February 2023
- January 31, 2023
This article with be updated as information on Kaipara's roading network is available.
Read more
Kaipara’s October roading report
- November 15, 2022
With the continued improvements in weather, we are now full swing into unsealed and sealed pavement works. We have approximately 50kms of road to reseal in the 2022/23 season.
Read more
Kaipara's September roading report
- October 11, 2022
Our roading team made the most of the warmer, drier weather that came our way in September.
Read more
Kaipara's August roading report
- September 09, 2022
August brought a welcome reprieve from the wild weather and storm events of July. A total of 3,100 individual work items were completed throughout August.
Read moreKaipara's July roading report
- August 18, 2022
Wild, wet and windy weather kept crews busy in July. A total of 3,358 individual work items were completed throughout the month.
Read more